INVENERGY'S SPINDLE HILL ENERGY CENTER AND SQUIRREL CREEK ENERGY CENTER

Invenergy was awarded a contract for a 250 MW natural gas peaker power plant by Xcel.  The Spindle Hill plant needed to be located in northern Colorado and the Squirrel Creek facility in southern Colorado near an Xcel transmission line with capacity and construction started within 16 months.  AquaSan found the site which had access to a natural gas line and an Xcel transmission line; however, no water and was zoned agricultural.  Project required extensive community interaction and commercial and regulatory negotiations.  Spindle Hill Project was approved and construction started in 11 months.  Squirrel Creek had similar challenges and similar time frame.  Water negotiations required the approval of four water providers and State, and zoning approval required extensive community negotiations and discussions.  Project was approved and water acquired within 13 months.

 

INVENERGY ENERGY PROJECTS - CALIFORNIA

Invenergy decided that it wanted to do wind and thermal energy development in California and requested AquaSan to help troubled sites and/or develop new sites in California.

 

LASSEN COUNTY WIND DEVELOPMENT     

Development was stalled due to Planning Commission denial of permit request,  the classification of the project area by the BLM as a view sensitive area, and inability to reach agreement with Lassen County Municipal District for transmission access.  Project required significant community organization, political work in Sacramento and Washington, and economic and environmental analysis for public education.  The Planning Commission approved the project, BLM has accepted the wind turbines in the view shed, and LMUD has approved a Letter of Understanding for use of their transmission lines. 

 

SAN DIEGO WIND DEVELOPMENT 

Development was stalled due to regulatory approval constraints.  Asked to assist local developer in moving project forward.  Required getting County Supervisor approval for new permitting process and obtaining support of local community leaders and organizations.  Project now has extensive community support and developed strong relationship with indian tribes.  After developing bid, Invenergy has been awarded  a 300 MW project on the Campo Reservation.

 

FRESNO COUNTY THERMAL DEVELOPMENT

Invenergy wants to develop a 550 MW energy center in Fresno County.  The energy center would require transmission, natural gas, and water.  AquaSan has found and contracted for sites that meet these requirements.  AquaSan also identified customer for the power and a partner for development in Kings River Conservation District.

 

CHERRY CREEK VALLEY WATER AND SANITATION DISTRICT

Aquasan Network was retained by the Cherry Creek Valley Water and Sanitation District, a rapidly growing district in the Denver Metropolitan area, to devise an alternative to a highly risky project for developing new water supplies.

The District was faced with water supply shortages and increasing costs and risks associated with development of new supplies.   They were considering participating in a highly risky project that would have required an investment of $15,000 per acre-foot and eleven years for development and construction.  

AquaSan Network devised a plan to develop the water in their watershed at a cost of $1,000 per acre-foot.  The water rights were applied for, negotiated and decreed within three years. 

 

LEGACY PARTNERS

Aquasan Network worked with Legacy Partners, a multi family developer, and two local municipalities to develop a  win/win solution to water and sanitation issues.  

Legacy Partners was developing a multi-family development that straddled two Colorado municipalities: Glendale and Denver.  These municipalities had separate sanitary sewer and water systems and, initially, were going to require the construction of two separate systems to serve this single development. 

AquaSan Network successfully negotiated an agreement on the developers behalf, with both municipalities, that allowed the developer to construct only one water and one sanitary sewer system at a savings to the client of $765,000. 

 

ARCHSTONE COMMUNITIES (SEATTLE, WASHINGTON)

Aquasan Network assisted Archstone Communities in verifying water availability for a project in Seattle Washington.

Archstone Communities faced a moratorium on the sale of new water taps in the Seattle, Washington area because the water provider perceived a water shortage.   

AquaSan Network provided data to the water provider verifying that the estimated demands of the Archstone project were significantly less than the provider had projected and that their project could proceed within the existing supply limitations.   As a result of this information, the Archstone project was approved and constructed on schedule.

 

PROSPECT RIDGE SUBDIVISION

 BENNETT, COLORADO

Aquasan Network was retained to assist West Bennett Associates address water acquisition and infrastructure development issues with the Town of Bennett, Colorado.

West Bennett Associates owned 320 acres of land in the Bennett, Colorado area wished to annex and develop the property in the Town.  The Town did not have sufficient water supply or facilities to serve the property.  The Town was requiring West Bennett Associates to extend water and sewer lines two miles to the property, build new water storage facilities and acquire additional water to meet the Towns' perceived demands from the project.  

AquaSan Network worked closely with the Owner to analyze the existing water supply and identify the demands of the project on the Town’s existing and proposed facilities.  West Bennett Associates entered into an annexation agreement with the Town that saved the Owner's $835,000 dollars in water right acquisition and facility development costs.

 

CITY OF CHERRY HILLS VILLAGE, COLORADO

Aquasan Network  was retained by the City of Cherry Hills Village to assist them in the consolidation and integration of individual water and sewer service contracts serving residents of the City.

The City of Cherry Hills Village, one of the most affluent City's in the nation, had 46 water and sewer contracts serving residents within the city boundaries.  This myriad of providers had uncoordinated water and sanitary sewer supply systems, resulting in less than adequate service to City residents.  The City determined that it was necessary to develop one coordinated system for water and sanitary sewer service.  To accomplish this goal, it was necessary to negotiate agreements with the separate water and sewer providers and to dissolve the existing in-city distributors and consolidate them with the City’s program. 

AquaSan Network negotiated service agreements, to serve the entire City, with each of the water providers (the City of Englewood, Colorado and the Denver Water Board) and each of the sanitary sewer service entities (the City of Englewood and the Metropolitan Wastewater Reclamation District).  Each existing distributor was then required to meet standards established by the new water and sanitary sewer service providers.  AquaSan Network negotiated with each distributor to tax or assess themselves in order to upgrade their systems and obtain the necessary easements for the construction of new facilities.  The project is still continuing today, and currently, more than 65% of the City is provided service with a system that meets existing standards.